Here at Tandridge Leisure Centre, our goal is to provide you with the very best facilities you deserve.
 
On Monday 29th September, we will begin our three phase Regeneration Project to make the wet side facilities the best they can be.
 
Phase 1
 
Sauna and Steam Room (29th Sept – 3rd Oct)
 
  •  Removal of old timber above the facilities
  •  Installation of a damp-proof membrane and new cladding
  • Improvements to ventilation and internal finishes
 During this time, both the sauna and steam room will be unavailable.
 
Poolside Beach Area and Slide (29th Sept – 3rd Oct)
 
  •  Removal of damaged mosaic tiles
  • Installation of new mosaic tiles to the pool surrounds
Work will be completed out of hours where required.
 
Phase 2
 
Female Wet Side Toilets (6th – 10th Oct)
  • Removal of old units, fittings, mirrors, and lighting
  • Deep cleaning and refurbishment of tiled floors and walls
  • Installation of new vanity units, shower and cubicle doors and walls, extractor fans, and lighting
Toilets closed for around 5 days
 
Phase 3
 
Male Wet Side Toilets (13th – 17th Oct)
 
  • Renovation following the same process as the female wet side toilets
 
While each toilet area is closed, customers will be able to use the alternative toilets located downstairs outside the pool hall, with signage provided to guide you.
 