Refurbishment underway at The Village Health Club

October 4 2018

We are pleased to announce our refurbishment commences from friday 8 October - tuesday 20 november

  • The schedule of refurbishment works at the Village Health Club is due to start from Friday 5 october – 20 november.
  • We will keep the centre open during this time, however there will be some disruption which is inevitable as both changing rooms will be undergoing a complete building refurbishment.
  • The first area of works will be the main corridor with new Karndean flooring and redecoration from friday 8 october – tuesday 16 october.
  • The contractor will then move on to the Male Changing Room which will take two weeks from thursday 11 – monday 29 october and will include new flooring, new benches, redecoration, new shower cubicles/re-tiling and general uplift
  • This will be repeated in the Female change from tuesday 30 october – monday 15 november.
  • We then start redecoration on the landing and gym stairs area which completes on tuesday 20 november.

The plan is to set up temporary changing for the males on poolside (where the sunbeds are by the window) and then in order to start work on the female changing room, we will move female changing into the refurbished male changing (with very very bold signage) and reception will be reminding members on entry to the centre.

This plan has been formulted impact the least number of customers possible, since the centre's membership is split 60/40% females to males. By keeping a female changing room open the whole time, the disruption effects the least number of customers possible and takes into account the majority of swimming lesson parents being female.